Eaton's 2-MW solid-state transformer clears UL tests

CEO Paulo Ruiz says the 800-volt DC shift is real on customer power savings, but the build-out timing is not Eaton's to set.

18%possible cut in non-IT data center capex

At a glance

  1. Utility Dive reported the remarks.
  2. Data centers built on the 800-volt DC architecture could cut non-IT capital expenditure by up to 18%, according to a McKinsey analysis cited by Utility Dive.
  3. Solid-state transformers use magnets and semiconductors instead of specialized steel alloys and large amounts of copper wiring, making them more compact and efficient than the low- and medium-voltage transformers they would replace.

Eaton's 15-kV, 2-MW solid-state transformer became, "to our knowledge," the first multi-megawatt unit to pass all tests under a new UL Solutions standard for the technology, CEO Paulo Ruiz said Tuesday. Utility Dive reported the remarks.

Data centers built on the 800-volt DC architecture could cut non-IT capital expenditure by up to 18%, according to a McKinsey analysis cited by Utility Dive.

Solid-state transformers use magnets and semiconductors instead of specialized steel alloys and large amounts of copper wiring, making them more compact and efficient than the low- and medium-voltage transformers they would replace. Eaton paid $86 million in August 2025 for Resilient Power Systems, a developer of the technology. A 1-MW solid-state transformer tested earlier this year by the Electric Power Research Institute, the New York Power Authority and North Carolina State University under what the report described as real-world conditions halved power losses against a traditional transformer configuration.

For an allocator underwriting a data-center development, the 18% is a planning number with a date attached. It applies to non-IT capital costs, so it moves the plant budget, not the servers: switchgear, breakers, transformers and the cooling that sits alongside them. The saving only reaches a model once equipment specified for 800V DC is available on the build schedule. Ruiz said the timing is not Eaton's to set. That leaves the electrical architecture as an assumption to test in diligence.

Ruiz said announced data-center projects worldwide amount to 366 GW, against 50 GW of installed capacity. He said he sees no letup in demand from data centers and utilities. Eaton, headquartered in Ireland and described by Utility Dive as one of the largest suppliers in the U.S. market, reported record third-quarter sales of $8.9 billion, up 28% year over year. Modular designs are compressing build schedules: as Private Wealth Daily previously reported, Nvidia says its DSX POD cuts data center build to 14 days, with 17 partners due to deliver the units worldwide in early 2027.

Solid-state transformers are one of several "key building blocks" an 800-volt DC design needs, Ruiz said, alongside DC breakers, power quality equipment and advanced cooling. "The AC architectures are not bad, and we are fine either way," he said. "We win in either path."

The UL result settles one component of the design. Whether developers commit to 800-volt DC depends on the rest of that equipment set reaching the same readiness.

Reported by the Data centers & fiber desk from Utility Dive. Published . Corrections

Related

Infrastructure

Infineon to supply silicon carbide devices for Eaton's 800VDC transformer platform

The two firms say silicon carbide will cut conversion losses in Eaton's MVSST 2.0 platform; no customer, site or delivery date is attached.

Infrastructure

Trane and Eaton pair power and cooling in one AI data center design

The companies say their reference design cuts energy use 15 percent and copper 80 percent.

Infrastructure

Deutsche Telekom to add 20MW of Nvidia B300 capacity in Munich

The expansion is about 15% of the 130MW that the carrier's T-Systems unit runs across 16 data centers.

Infrastructure

Kraft Group weighs 900MW data center campus in Massachusetts

The town manager's memo projects more than $16 billion of private investment, ten buildings by 2033 and a town vote in May 2027.

Infrastructure

LDA to convert three supply vessels into cable ships

The converted vessels will join a subsea cable fleet of 12 ships, six laying and six maintenance.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections