Skip to content
Thursday, October 29, 2026 · Today’s edition, 6:30 a.m. ETThu, Oct 29 · 6:30 a.m. editionSign inMy Desk 0EditionsSign in

Enverus: SPP leads large-load readiness while PJM holds largest pipeline

SPP has the most advanced framework but about 5% of the high-confidence pipeline; PJM's 11.8 GW is 58% expected to be served behind the meter.

At a glance

  1. PJM holds the largest high-confidence data center pipeline in that assessment, at about 11.8 GW.
  2. Enverus scored each operator against the five reform areas FERC identified in its June 2026 show-cause orders.
  3. SPP's High Impact Large Load and High Impact Large Load Generation Assessment frameworks pair generation with load, reduce network upgrade costs, facilitate colocation, limit cost sharing to ratepayers and improve study efficiency.

SPP is the only region with FERC-approved large-load tariffs, according to Enverus Intelligence Research's grading of ISO and RTO large-load readiness. PJM holds the largest high-confidence data center pipeline in that assessment, at about 11.8 GW.

Enverus scored each operator against the five reform areas FERC identified in its June 2026 show-cause orders. Those orders required every grid operator to prove its interconnection framework can handle the 62 GW of new U.S. data center capacity expected by 2030.

SPP's High Impact Large Load and High Impact Large Load Generation Assessment frameworks pair generation with load, reduce network upgrade costs, facilitate colocation, limit cost sharing to ratepayers and improve study efficiency. Its Conditional High Impact Large Load Service goes further: it enables an almost immediate grid connection for a new or expanding large load, provided the developer accepts conditional, non-firm service for seven years during upgrades and carries peak-demand curtailment risk.

SPP holds only about 5% of the high-confidence pipeline, which Enverus defines as projects where the developer has land ownership and access to power, gas and fiber. Reform is uneven across FERC-jurisdictional regions, and a few operators have barely started.

PJM's pipeline leans behind the meter

PJM's 11.8 GW is the largest high-confidence pipeline in the assessment, and 58% of it is expected to be served behind the meter. That split suggests developers in the region are prioritizing speed to power over the interconnection queue: a behind-the-meter project would still need generation, fuel and permits, but it would shift the timing question onto the developer's own procurement rather than the operator's study process.

FERC is not pushing a single template; Enverus notes the commission encouraged operators to tailor reforms to their systems. The result is a patchwork of timelines, costs and risk that developers and investors must navigate largely on their own, while utilities carry the burden of rewriting operational playbooks, planning for short-term grid impacts and revising capital expenditure forecasts.

Reported by the Data centers & fiber desk from Utility Dive. Published . Corrections

Related

Infrastructure

FERC rejects PJM's backstop cost allocation, leaving the 6.8 GW auction unscheduled

PJM had planned to take offers from Sept. 30 through Oct. 21 for capacity covering a shortfall driven largely by data center demand forecasts.

Infrastructure

SoftBank asks PJM to study 10-GW Ohio data center complex under state agreement

The filing pairs 9.6 GW of added load with 10.2 GW of SB Energy gas-fired generation through 2032 and three new AEP Ohio 765-kV lines.

Infrastructure

SPP's Western adequacy stop-gap draws four protests, including its own monitor

WAPA, Basin Electric and Guzman Energy seek changes to the Sept. 4 filing, which would run until June 1, 2027.

Infrastructure

Omnes Capital invests in Heim's Nordic data center platform

Three listed campuses total 180MW in first phases and scale to 580MW by 2030, with first projects in Finland.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections