Skip to content
Monday, November 2, 2026 · Today’s edition, 6:30 a.m. ETMon, Nov 2 · 6:30 a.m. editionSign inMy Desk 0EditionsSign in

Exelon weighs $3 billion to $7 billion for regulated storage

The range covers 1.5 GW to 3.5 GW and excludes a $1 billion, 500-MW project with Invenergy awaiting a New Jersey decision.

$3Bto $7 billion for regulated storage

At a glance

  1. The range excludes a $1 billion, 500-MW project with Invenergy pending before New Jersey regulators, Utility Dive reported.
  2. Three of the states where Exelon's utilities operate — New Jersey, Maryland and Delaware — let them own storage outright, CFO Robert Kleczynski said.
  3. For infrastructure allocators, the plan creates a second model for PJM storage: utility-owned assets recovered through customer rates, with the investment tax credit passed back to customers.

Exelon's utilities could spend $3 billion to $7 billion building 1.5 GW to 3.5 GW of regulated energy storage, executives said on the company's Friday earnings call. The range excludes a $1 billion, 500-MW project with Invenergy pending before New Jersey regulators, Utility Dive reported.

Three of the states where Exelon's utilities operate — New Jersey, Maryland and Delaware — let them own storage outright, CFO Robert Kleczynski said. "With regulated storage, we have certainty that projects get built, and control over when and how they're deployed," he said. He described utility-owned storage as one option alongside competitive development, not a replacement for it.

For infrastructure allocators, the plan creates a second model for PJM storage: utility-owned assets recovered through customer rates, with the investment tax credit passed back to customers. Kleczynski said customers would gain through lower capacity prices and the credit flow-through would ease the effect on electricity rates. Because spending runs through state commissions rather than PJM's capacity auction, returns will likely be set by regulatory approval and cost recovery rather than market clearing prices.

Atlantic City Electric's 500-MW project with Invenergy, already before New Jersey regulators, would be the largest battery installation in PJM, Kleczynski said. He said it is expected to provide more than $700 million in net benefits to customers.

The storage plan is aimed partly at a supply gap that CEO Calvin Butler says PJM is not closing fast enough. The grid operator's backstop capacity procurement plan and Interim Resource Adequacy Service proposal have been delayed by partial approvals at the Federal Energy Regulatory Commission.

The New Jersey Board of Public Utilities is expected to decide on the Atlantic City Electric project late in the first quarter of next year, the first test of the storage budget.

Two storage bets: $3B-$7B planned, $1B pending

Budget and capacity for Exelon's regulated storage build versus the Atlantic City Electric project

Regulated storage build

$3B-$7B

Capacity
1.5-3.5 GW
Ownership
Utility-owned
States
NJ, MD, DE
Cost recovery
Customer rates

Atlantic City Electric

$1B

Capacity
500 MW
Partner
Invenergy
Status
Pending at NJBPU
Net customer benefit
$700M+
Source: Exelon earnings call via Utility Dive
Show as table
Regulated storage buildAtlantic City Electric
Figure$3B-$7B$1B
Capacity1.5-3.5 GW500 MW
OwnershipUtility-owned
StatesNJ, MD, DE
Cost recoveryCustomer rates
PartnerInvenergy
StatusPending at NJBPU
Net customer benefit$700M+
With regulated storage, we have certainty that projects get built, and control over when and how they're deployed.Robert Kleczynski, Exelon's chief financial officer

Reported by the Energy Transition desk from Utility Dive. Published . Corrections

Related

Infrastructure

Winter reliability now rides on interregional transfers

Peak outages fell sharply from Elliott and Uri; FERC/NERC credit coordination and transfers, not new steel.

Infrastructure

Constellation signs 890-MW Google nuclear PPA as PJM backstop stalls

The 20-year agreement and a companion Amazon contract support almost 1.1 GW of expansion at existing reactors, with no price disclosed.

Infrastructure

Washington's grid money stops buying new corridors

The $1.9 billion SPARK package buys 23 gigawatts on lines that already exist, turning the data center buildout's power schedule into a question of tariff design.

Infrastructure

Qualitas Energy secures $286M for Chilean renewables

The nonrecourse financing covers an operating hydro group and 193 megawatts of solar and wind under construction for 2028 completion.

Infrastructure

Mitsubishi Electric infrastructure revenue rises 20% before PCI close

The Infrastructure segment took in ¥379.7 billion in the fiscal second quarter as the $1.4 billion PCI Energy Solutions purchase is expected to close by end-2026.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections