Google agreed in June to fund a 100-MW Voltus virtual power plant in PJM

Voltus carries Google's capacity obligation under a three-year contract that pays PJM customers to participate.

At a glance

  1. Voltus will operate the three-year program and carry Google's capacity obligation in the regional market.
  2. The arrangement pays residential, commercial and industrial PJM customers to participate, so the capacity Google is buying comes from demand reduction spread across the market rather than from a plant it owns.
  3. Jon Wellinghoff, Voltus's chief regulatory officer and a former chair of the Federal Energy Regulatory Commission, described the contract as "a turning point — allowing markets to treat distributed capacity like any other capacity resource."

Google agreed in June to fund a 100-MW virtual power plant in PJM Interconnection, Utility Dive reported Oct. 19. Voltus will operate the three-year program and carry Google's capacity obligation in the regional market.

The arrangement pays residential, commercial and industrial PJM customers to participate, so the capacity Google is buying comes from demand reduction spread across the market rather than from a plant it owns. Voltus chief executive Dana Guernsey compared such "bring your own new capacity" contracts to the power purchase agreements that she said revolutionized utility-scale solar and wind development.

Jon Wellinghoff, Voltus's chief regulatory officer and a former chair of the Federal Energy Regulatory Commission, described the contract as "a turning point — allowing markets to treat distributed capacity like any other capacity resource." He said large loads such as data centers are now contracting with distributed capacity providers for utility-scale bring-your-own-new-capacity.

Demand for capacity in PJM exceeds supply even at record-high prices, Mary Yang, an energy lawyer and chief operating officer at consulting firm 804 Advisory, told Utility Dive. Interconnection queues at PJM and other regional grids run years long while regulators weigh market reforms, the report said.

What 100 megawatts buys

PJM set a record peak load of 168.2 GW on July 2, per the report. That makes 100 MW about 0.06% of that day's peak demand, a comparison of contracted capacity against one day's peak, not a like-for-like measure. Industry experts quoted by Utility Dive describe distributed capacity as faster and easier to integrate than traditional capacity resources. The contract tests whether a large load can meet a capacity obligation by contracting for demand rather than building generation.

Pier LaFarge, chief executive of Sparkfund, told Utility Dive the system still needs investment in transmission, centralized generation and storage to meet load growth and cut the cost of electricity. Sparkfund is working with Xcel Minnesota on the utility's Capacity*Connect distributed capacity pilot. He also said it needs operational flexibility from large loads, especially data centers. Lon Huber, Xcel's senior vice president for integrated system planning and chief planning officer, said distributed capacity done right can unlock beneficial load growth, raising grid utilization and putting downward pressure on rates.

Large loads are increasingly priced on explicit capacity commitments rather than queue position, a shift Utility Dive has traced. LaFarge said distributed capacity as a category of resource to meet system needs has arrived.

Reported by the Energy Transition desk from Utility Dive, Canary Media, Data Center Dynamics and Utility Dive. Published . Updated Oct 27, 2026 · 10:24 a.m. ET. Corrections

Related

Infrastructure

Google and Voltus expand PJM virtual power plant to 1,170 MW

The expansion adds 1,070 MW to the June 100 MW program, with a three-to-four-year ramp and a 2040 term.

Infrastructure

Sunrun, Voltus turn home batteries into AI data center capacity

A distributed-energy pact lets hyperscaler-backed data center developers bring residential capacity to PJM and MISO interconnections.

Infrastructure

Innio adds 620MW of gas engines as DOJ targets wind permits

The 1.72GW contracted book includes a maintenance agreement covering the first 500MW, while three offshore wind projects face revocation motions.

Infrastructure

PJM takes steps to speed grid battery connections

The biggest US grid operator serves 13 states and its grid is congested, Canary Media reports.

Infrastructure

DOE commits $10.1 billion in loans to Constellation and Alliant

Alliant's $5.1 billion has closed across two subsidiaries while Constellation's conditional share must clear technical, legal, environmental and financial conditions.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections