Google backstops TeraWulf's 480MW Anthropic data center financing

The Justified campus in Kentucky is leased to Anthropic for 20 years under a $19 billion contract.

Watch

Anthropic Might Be Proving the AI Bears Wrong

The Compound (Ritholtz Wealth)Video2 min

At a glance

  1. Under the credit support agreement, Google will backstop the anticipated debt financing TeraWulf needs to develop the project and would take responsibility for the debt should the developer default.
  2. Lenders will underwrite the construction loan against Google's balance sheet instead of TeraWulf's, while the 20-year Anthropic lease supplies the revenue.
  3. The 790-acre Hancock County site was acquired from Century Aluminum, which operated there from 1969 to 2022.

TeraWulf secured Google as a credit backstop for the financing behind its Justified Data Campus in Hawesville, Kentucky, a 480MW project leased to Anthropic under a $19 billion, 20-year deal.

Under the credit support agreement, Google will backstop the anticipated debt financing TeraWulf needs to develop the project and would take responsibility for the debt should the developer default. Google's senior unsecured debt is rated AA+ by S&P Global Ratings and Aa2 by Moody's. Data Center Dynamics first reported the agreement. Reports in July 2026 said TeraWulf was seeking $3.5 billion of debt for the campus.

Lenders will underwrite the construction loan against Google's balance sheet instead of TeraWulf's, while the 20-year Anthropic lease supplies the revenue. TeraWulf said the support lowers its cost of borrowing. The financing Google would backstop has not yet been raised.

“We structured our Anthropic leases from the outset to address counterparty credit, financing costs and capital requirements,” said Paul Prager, TeraWulf's chairman and chief executive. He said Google's credit support strengthens the company's ability to secure competitive project financing.

The 790-acre Hancock County site was acquired from Century Aluminum, which operated there from 1969 to 2022.

TeraWulf also signed a definitive engineering, procurement and construction agreement with Fluor covering three data center buildings at Justified, building on a limited notice to proceed announced in March 2026. Prager said Fluor's engineering depth and procurement reach let TeraWulf scale execution without building a global engineering and construction organization internally.

Google has backstopped TeraWulf before, on the developer's joint venture with Fluidstack. Anthropic has disclosed $895 billion of AI infrastructure commitments, as Private Wealth Daily previously reported.

The first facility on the site is due online in 2027.

“We structured our Anthropic leases from the outset to address counterparty credit, financing costs and capital requirements.”Paul Prager, chairman and chief executive of TeraWulf

Reported by the Data centers & fiber desk from Data Center Dynamics and TeraWulf announcement. Published . Updated Nov 5, 2026 · 6:47 p.m. ET. Corrections

Related

Infrastructure

Fluor wins EPC contract for TeraWulf's $4 billion Kentucky campus

The definitive award covers three buildings at the Justified Data Campus, with ready-for-service completions phased from late 2027 into mid-2028.

Infrastructure

TeraWulf to double Muskie contracted capacity to 1GW; second phase moves into 2029

The amended Kentucky Power agreement would raise contracted capacity at the Muskie Data Campus from 500MW to 1GW and pull the second 500MW phase forward a year, subject to state commission approval.

Infrastructure

TeraWulf pays the freight for 482MW Kentucky grid connection

By taking on full grid costs, TeraWulf turns Kentucky co-ops into financial partners, clearing the way for the Justified buildout.

Infrastructure

Kraft Group weighs 900MW data center campus in Massachusetts

The town manager's memo projects more than $16 billion of private investment, ten buildings by 2033 and a town vote in May 2027.

Infrastructure

LDA to convert three supply vessels into cable ships

The converted vessels will join a subsea cable fleet of 12 ships, six laying and six maintenance.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections