Granite and Super Excavators win $324.8 million Cleveland sewer tunnel contract

The Big Creek Tunnel is the seventh and final large-diameter storage tunnel in the sewer district's $3 billion Project Clean Lake.

At a glance

  1. The work is large-diameter tunneling in the plainest sense: 22,300 linear feet of 20-foot-diameter bore plus 3,115 linear feet of ancillary tunnels, along with shafts, diversion structures, gate and screening structures, gate control vaults, consolidation sewers and an overflow box culvert, followed by associated sitework, restoration and utility relocations.
  2. The bore runs more than four miles through rock, between 50 and 100 feet beneath Cleveland, Linndale and Brooklyn.
  3. Across all seven tunnels the program is designed to hold back 4.5 billion gallons of overflow from Lake Erie, and the final contract arrives 15 years into that schedule.

The Northeast Ohio Regional Sewer District has awarded the Big Creek Tunnel contract to Granite Construction and Super Excavators, a $324.8 million job Granite announced in an Oct. 1 release. The award marks the seventh and final large-diameter storage tunnel under the district’s $3 billion Project Clean Lake, and it arrives with no public account of how that program is financed.

The work is large-diameter tunneling in the plainest sense: 22,300 linear feet of 20-foot-diameter bore plus 3,115 linear feet of ancillary tunnels, along with shafts, diversion structures, gate and screening structures, gate control vaults, consolidation sewers and an overflow box culvert, followed by associated sitework, restoration and utility relocations. Granite, based in Watsonville, California, is joined by Menomonee Falls, Wisconsin-based Super Excavators on the job.

The bore runs more than four miles through rock, between 50 and 100 feet beneath Cleveland, Linndale and Brooklyn. Once the structures are in place, the district expects them to eliminate 550 million gallons of combined sewer releases each year, keeping that volume out of Lake Erie and the surrounding waterways.

Big Creek is the seventh and final large-diameter combined sewer overflow storage tunnel under Project Clean Lake, the district’s $3 billion, 24-year program launched in 2011 to meet Clean Water Act standards and improve regional water quality. Across all seven tunnels the program is designed to hold back 4.5 billion gallons of overflow from Lake Erie, and the final contract arrives 15 years into that schedule. Jim Nickerson, vice president of Granite’s tunnel division, said in the release that the project’s “scale and complexity” align with the contractor’s strengths in large-diameter tunneling and shaft construction.

Public water work has been a reliable source of big prime contracts in 2026, with the release listing a $1 billion Ohio River Tunnel contract in Allegheny County, Pennsylvania, for a joint venture of Lane Construction and Brayman Construction, and a $518 million floodwater project in Virginia that FlatironDragados began construction on earlier in the year. In June the U.S. Department of Transportation earmarked $1.86 billion for infrastructure damaged by storms, water systems among it, following Hurricane Helene in September 2024.

How Project Clean Lake is financed—the mix of debt, grants or rate revenue—and the district’s remaining procurement calendar have not been disclosed. That gap is the ordinary condition of municipal utility tunneling: the award is public, the capital behind it is not, and the private funds this desk usually follows appear nowhere in the paperwork. With all seven storage tunnels now spoken for under this program, the next awards of comparable size in the region will run through other owners’ programs, as the Allegheny County and Virginia jobs already suggest.

2026 public water contracts cited in the award release

  • Ohio River Tunnel · Allegheny County, PA$1K
  • Floodwater project · Virginia$518M
  • Big Creek Tunnel · Cleveland$324.8M
Source: Granite release and agency reports via Construction Dive · Oct 2026
Show as table
ItemValue ($M)
Ohio River Tunnel · Allegheny County, PA$1K
Floodwater project · Virginia$518M
Big Creek Tunnel · Cleveland$324.8M

Reported by the Fundraising desk from Construction Dive and Granite Construction news release, Oct. 1 (cited within Construction Dive). Published . Updated Oct 27, 2026 · 1:16 p.m. ET. Corrections

Related

Infrastructure

Tutor Perini unit Fisk Electric picked for Houston data center electrical work

Electrical construction is expected to begin this year and reach substantial completion in the first quarter of 2027, Construction Dive reports.

Infrastructure

Foundation Credit closes $540M infrastructure debt fund above target

The close came a week after Foundation Credit announced a majority investment from New Holland Capital.

Infrastructure

EdgeCore closes $521 million green ABS on Santa Clara campus

The 36MW SV01 data center backs the deal, EdgeCore's second securitization, which is more than double last year's $235 million Phoenix issue.

Infrastructure

KBRA assigns preliminary A- to up to $525 million US Signal ABS

Ten existing colocation sites with $111.8 million of annualized recurring revenue back the three-tranche deal, which carries a 12% stressed terminal cap rate.

Infrastructure

EdgeCore, US Signal push data center ABS past $1 billion

EdgeCore's $521 million green ABS closed on a Santa Clara campus, more than double its previous Phoenix issue.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections