Kraft Group weighs 900MW data center campus in Massachusetts

The town manager's memo projects more than $16 billion of private investment, ten buildings by 2033 and a town vote in May 2027.

$16BEstimated private investment in the 900MW Sutton campus

At a glance

  1. The estimate comes from a memo by town manager Austin Cyganiewicz to the Select Board, first reported by Data Center Dynamics.
  2. The first two buildings would each cover about 250,000 square feet and carry roughly 90MW of power capacity, with a planned launch in 2029.
  3. For an equity partner or lender weighing a 2029 opening, the May 2027 town vote and local approval conditions are the schedule to underwrite.

The Kraft Group could build a 900MW data center campus in Sutton, Massachusetts, representing more than $16 billion of private investment. The estimate comes from a memo by town manager Austin Cyganiewicz to the Select Board, first reported by Data Center Dynamics.

The first two buildings would each cover about 250,000 square feet and carry roughly 90MW of power capacity, with a planned launch in 2029. The campus would sit on the Parkway property of Unified Global Packaging Group, a Sutton-based packaging firm, off Boston Road and Providence Road. Two more buildings would follow each year through 2033, taking the site to ten buildings and about 900MW at full build-out, based on the developer's estimates cited in the memo.

For an equity partner or lender weighing a 2029 opening, the May 2027 town vote and local approval conditions are the schedule to underwrite. Under an executive order from Governor Maura Healey, data centers over 25MW proposed in Massachusetts must be approved by local communities, and developers must implement a community benefits agreement.

The memo estimates the property would pay about $10.4 million a year once fully assessed in 2031, rising to $27.8 million at full build-out. Sutton's entire 2027 tax levy is projected at $32 million, and the assessed value of all property in town is $2.7 billion.

"Because the town raises only what its budget requires, the main effect would be lower tax bills," Cyganiewicz wrote, putting the reduction at about $2,300 for the average single-family home in FY2031 and about $5,800 in FY2035.

The proposal is tentative and no formal application has been filed. Cyganiewicz said discussions are under way with the regional grid operator, and cooling would use reclaimed water. At the Nov. 10 Select Board meeting, residents raised concerns about noise from an operating data center and about a possible town moratorium, according to social media comments after the session cited by Data Center Dynamics.

Cyganiewicz laid out approval on parallel tracks, with community benefits discussions, zoning bylaws and a technical review all running toward a town meeting and vote in May 2027.

One campus could nearly match Sutton's entire tax levy

Projected annual property tax from the campus vs. Sutton's whole 2027 levy, $M

  • Sutton's 2027 tax levy$32M
  • Campus at full build-out$27.8M
  • Campus when fully assessed, 2031$10.4M
Source: Sutton town manager memo to the Select Board
Show as table
ItemValue ($M)
Sutton's 2027 tax levy$32M
Campus at full build-out$27.8M
Campus when fully assessed, 2031$10.4M

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Real Estate

Massachusetts awards $330M in largest One Stop round to 403 projects

The state estimates the awards will help unlock $24.6 billion in private investment and support more than 27,000 new homes.

Real Estate

Healey's data center order reprices power, and the megawatts will move

Massachusetts has made grid cost and town consent conditions of entry; private capital's answer is to site the megawatts somewhere else.

Real Estate

Massachusetts puts local sign-off ahead of data center permitting

Developers must clear community benefits agreements before state agencies act, adding unquantified duration to Bay State data center schedules.

Infrastructure

LDA to convert three supply vessels into cable ships

The converted vessels will join a subsea cable fleet of 12 ships, six laying and six maintenance.

Infrastructure

JGT2 seeks Maine permits for data center at former Androscoggin mill

The Nov. 8 filing revives a data center plan whose original partner, Sentinel Data Centers, left in June.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections