Skip to content
Tuesday, October 27, 2026 · Today’s edition, 6:30 a.m. ETTue, Oct 27 · 6:30 a.m. editionSign inMy Desk 0EditionsSign in

MISO 120-day load study draws state, Google objections at FERC

Eleven state utility commissions backed OMS's protest; MISO files a cost-allocation framework next month.

At a glance

  1. MISO proposed the process earlier this month.
  2. The Organization of MISO States told FERC that a majority of its members have "significant concerns," including cost-shifting risks to existing customers and potential effects on competition.
  3. Google and a coalition including the Sierra Club and the Natural Resources Defense Council said in separate filings that the proposal would leave existing customers paying for network upgrades needed for new loads and generation.

MISO's proposed 120-day LARS study track for loads over 200 MW paired with generation in the same local resource zone drew FERC objections from a majority of state utility commissions, Google and environmental groups.

MISO proposed the process earlier this month. Under the proposal, MISO would study planned load and generation at the same time. The application says the track responds in part to FERC's mid-June finding that its large-load rules are inadequate, including for integrating "proximate" loads and generation. MISO would accept applications only from transmission customers, meaning an independent generator would need a utility sponsor; critics said that favors vertically integrated utilities over independent producers.

The Organization of MISO States told FERC that a majority of its members have "significant concerns," including cost-shifting risks to existing customers and potential effects on competition. OMS said LARS cannot become a general alternative to the existing generation interconnection queue or provide preferential access to transmission capacity without adequate safeguards for existing queue participants and transmission customers. It added that any LARS-like program should end after five years.

Google and a coalition including the Sierra Club and the Natural Resources Defense Council said in separate filings that the proposal would leave existing customers paying for network upgrades needed for new loads and generation. Google said the absence of cost-shifting protections is especially concerning because the structure threatens its commitment that other retail customers not bear the costs of serving its data centers, including through its Ratepayer Protection Pledge. Google has been funding grid and storage for its own data centers, as Private Wealth Daily previously reported, including a 600 MW project in Arkansas this month. MISO's cost-allocation details, Google said, are "open questions, which the Commission cannot simply assume away."

Eleven state utility commissions backed OMS's comments, while commissions in Arkansas, Louisiana and Mississippi filed in support of MISO's plan. Ratepayer advocates representing six states also opposed the proposal, partly over cost-shifting concerns.

The cost-allocation framework MISO files next month will determine who pays for the network upgrades the paired load and generation require. OMS wants a five-year sunset written into any LARS program. FERC will weigh those terms against MISO's argument that the track speeds grid access for new large loads.

Reported by the Energy Transition desk from Utility Dive. Published . Corrections

Related

Infrastructure

MISO asks FERC to approve penalty-free queue exits by Oct. 19

The filing would let 2022-cycle projects withdraw without penalty until Decision Point II on Oct. 20 and lift the network-upgrade cost trigger for later exits to 50%.

Infrastructure

NERC stakeholders back draft reliability rules for 50MW-plus compute loads

The draft covers 50 MW-plus AI data centers and crypto miners at 100 kV or above; the next step is the NERC board, then FERC.

Infrastructure

SoftBank asks PJM to study 10-GW Ohio data center complex under state agreement

The filing pairs 9.6 GW of added load with 10.2 GW of SB Energy gas-fired generation through 2032 and three new AEP Ohio 765-kV lines.

Infrastructure

US wind orders hit 2.8 GW in Q2 before tax credit cutoff

Wood Mackenzie keeps a 39 GW onshore outlook through 2030 and says more than half of the 2026–2028 pipeline is operating or under construction.

Infrastructure

Data center power demand nears 20% a year; procurement is the risk

Transparent Energy's Dustin Scarpa says suppliers price load shape, credit, collateral and start-date certainty, not just scale, into a data center's power contract.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections