Soluna files for 112MW Kati II data center in Willacy, Texas

The Texas filing estimates $471.8 million for a single 471,884 sq ft building and gives no construction timeline.

At a glance

  1. On the filing's figures, the build works out to roughly $4.2 million per megawatt and about $1,000 per square foot.
  2. Data Center Dynamics describes Kati II as seemingly an extension of the company's Kati I data center, which has 166MW of planned capacity at full buildout and 83MW in a first phase.
  3. If built, Kati II's 112MW would add roughly 58% to Soluna's reported operating capacity of 192MW.

Soluna has filed to build a 112MW data center called Kati II in Willacy, Texas, according to a filing first reported by Data Center Dynamics on Oct. 14. The filing with the Texas Department of Licensing and Regulation estimates $471.8 million for the single 471,884 sq ft (43,839 sqm) building.

On the filing's figures, the build works out to roughly $4.2 million per megawatt and about $1,000 per square foot.

Data Center Dynamics describes Kati II as seemingly an extension of the company's Kati I data center, which has 166MW of planned capacity at full buildout and 83MW in a first phase. Soluna confirmed a definitive joint venture agreement for Kati II with Metrobloks on June 3.

If built, Kati II's 112MW would add roughly 58% to Soluna's reported operating capacity of 192MW. In August it acquired a 397-acre plot in Briscoe County, Texas, for a Dorothy III campus of up to 300MW, adjacent to Dorothy I and II and next to the 150MW Briscoe wind farm it bought in April.

ProjectCapacityStatus per filing and reporting
Kati II (Willacy, Texas)112MWFiled; no timeline given
Kati I (Willacy, Texas)166MW planned; 83MW Phase IPhase I completed September 2026
Project Rosa187MWListed among 11 sites in development
Dorothy III (Briscoe County)Up to 300MWLand acquired August 2026

Reported by the Data centers & fiber desk from Data Center Dynamics, Texas Department of Licensing and Regulation filing and Private Infrastructure Daily archive. Published . Corrections

Related

Infrastructure

Anthropic in talks for second 460MW lease at Nscale's West Virginia campus

The reported contract would double Anthropic's committed capacity at Monarch to 920MW, while Microsoft already holds 1.35GW at the same West Virginia campus.

Infrastructure

Soluna and Applied Digital agree 50MW Texas data center joint venture

Applied is expected to hold 51% and supply capital; ChronoScale has signed a non-binding letter of intent to lease the capacity.

Infrastructure

Stack Infrastructure affiliate files for second Lancaster data center building

The DFW02B filing carries a $540 million construction budget and a March 2027 to December 2028 schedule.

Infrastructure

Marwynn signs Grenada MoU for $500m solar and AI data center

The 24-month agreement gives Marwynn exclusivity to study land, grid and connectivity before committing capital.

Infrastructure

Chatterjee Group launches Cortex DC with 2 GW India target

The platform targets operational readiness within 18 months of breaking ground and plans to source 51% of its energy from green sources.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections