SWI launches AI cloud unit with 3.6GW of power

The unit will start with 30MW in Cambridge and targets 2.3GW of Nvidia-focused capacity by 2029.

At a glance

  1. Its first large-scale deployment in Cambridge will host close to 7,000 Nvidia Rubin GPUs and 3,500 Vera CPUs in Vera Rubin NVL72 racks, Data Center Dynamics first reported.
  2. The first 30MW is about 5% of the planned 530MW Cambridge campus, and the 2.3GW target is more than 70 times the first phase.
  3. SWI said it has finalized contracts with its first customers but did not disclose contract values, customer names or lease terms, leaving utilization and pricing as the key unknowns for allocators underwriting the buildout.

SWI Group on Monday launched SWI Compute, an AI cloud unit supported by 3.6GW of power capacity across 24 sites in the US and Europe, starting with 30MW at a planned Cambridge, UK, campus.

Its first large-scale deployment in Cambridge will host close to 7,000 Nvidia Rubin GPUs and 3,500 Vera CPUs in Vera Rubin NVL72 racks, Data Center Dynamics first reported. The first 30MW is expected online by the end of 2027 and is the initial phase of a UK campus planned to reach 530MW. SWI is targeting 2.3GW of Nvidia-focused capacity by 2029.

The first 30MW is about 5% of the planned 530MW Cambridge campus, and the 2.3GW target is more than 70 times the first phase.

SWI said it has finalized contracts with its first customers but did not disclose contract values, customer names or lease terms, leaving utilization and pricing as the key unknowns for allocators underwriting the buildout.

SWI Group, listed on Euronext Amsterdam, reports €11 billion ($12.27 billion) in assets under management, so the approximately $1 billion hardware order is equivalent to about 8% of AUM. Halil Mirakhmedov, CEO of SWI Compute, said the team secured those advanced Nvidia hardware orders after joining the Nvidia Cloud Partner program, and that SWI Group had spent six years acquiring grid access.

SWI Group was formed from the merger of Stoneweg and Icona Capital last year. It took a stake in AiOnX, which has data center projects in the UK, Ireland and mainland Europe, and said every SWI Compute site will be built to Nvidia reference architectures and DSX AI Factory Platform requirements.

SWI Compute's power ladder: 30MW at launch against 3.6GW secured

The first Cambridge phase is 5.7% of the planned campus

  • Power secured group-wide, 24 sites3.6K MW
  • Nvidia-focused capacity target, 20292.3K MW
  • Cambridge campus, planned530 MW
  • First Cambridge phase, end-202730 MW
Source: Data Center Dynamics · SWI Compute figures
Show as table
ItemValue (MW)
First Cambridge phase, end-202730 MW
Cambridge campus, planned530 MW
Nvidia-focused capacity target, 20292.3K MW
Power secured group-wide, 24 sites3.6K MW

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

SWI raises €800 million in equity for US and Europe data center buildout

The Euronext Amsterdam-listed investor says total equity raised since March 2026 now exceeds €1 billion ($1.1bn).

Infrastructure

NTT Data adds Paris and Singapore GPU capacity

The sites join Plano and Riyadh, giving NTT four AI factories plus an Nvidia GPU installation in Munich.

Infrastructure

Microsoft extends data center useful life to 25 years

Azure posted its first standalone revenue of $33.2 billion as capex of $45.2 billion landed below the $50.7 billion expected.

Infrastructure

Omnes Capital invests in Heim's Nordic data center platform

Three listed campuses total 180MW in first phases and scale to 580MW by 2030, with first projects in Finland.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections