DOE offers Vistra a $4.2 billion conditional loan for 433 MW of nuclear uprates

The commitment is tied to Vistra's 2.6-gigawatt Meta agreement and would preserve roughly 4 gigawatts of PJM nuclear, with funding awaiting technical, legal, environmental and financial reviews.

At a glance

  1. Perry, Davis-Besse and Beaver Valley would take the work.
  2. Funding awaits technical, legal, environmental and financial reviews, so the loan is an offer rather than a closed financing.
  3. At 433 megawatts, the uprates amount to about a sixth of the 2.6-gigawatt Meta agreement, which suggests the three plants' existing output carries most of that obligation.

The Department of Energy has offered Vistra a conditional $4.2 billion loan for 433 megawatts of nuclear uprates at three existing plants, our records show. Perry, Davis-Besse and Beaver Valley would take the work.

The commitment is tied to Vistra's 2.6-gigawatt Meta agreement and would preserve roughly 4 gigawatts of PJM nuclear capacity. Funding awaits technical, legal, environmental and financial reviews, so the loan is an offer rather than a closed financing.

At 433 megawatts, the uprates amount to about a sixth of the 2.6-gigawatt Meta agreement, which suggests the three plants' existing output carries most of that obligation.

Google and Constellation take the contract route

Google signed two Constellation Energy agreements totaling 3.6 gigawatts, our deal log shows. One is a 20-year nuclear contract covering 890 megawatts that enables $4.3 billion of Constellation equipment spending at 11 units. A second agreement runs 15 years and buys 2.7 gigawatts across PJM. No price was disclosed.

In both the Vistra and Constellation deals, capital goes to reactors that already hold licenses and grid connections rather than to new construction. Federal credit and hyperscaler offtake pay for that work.

Reported by The Wrap desk from Canary Media, Wood Mackenzie and Private Infrastructure Daily weekly coverage tracking. Published . Updated Oct 26, 2026 · 10:51 p.m. ET. Corrections

Private Wealth Daily member access

Continue this analysis

Get the complete Infrastructure analysis and every detail that follows.

Enter a valid work email to continue reading.

Private Infrastructure Daily, from Private Wealth Daily. Unsubscribe anytime.

Full featuresIn-depth analysis and exclusive reporting.
Source-backed contextEvidence, context and the complete story.
One login across the networkAccess every Daily Network publication.

Related

Infrastructure

PJM clears 2.1 GW as RWE adds EUR 3.6bn to its Amprion stake

Both PJM projects are expected online by mid-2029, after the expedited track that cleared them lapses at the end of 2027.

Infrastructure

Bain projects $5tn to $6.5tn data center spending through 2030

Power availability, electrical labor and local opposition are the near-term constraints, not capital.

Infrastructure

Google signs two Constellation contracts totaling 3.6GW; 890MW nuclear PPA funds $4.3B in uprates

A 20-year nuclear contract covers 890MW and enables $4.3 billion of Constellation equipment spending at 11 units; a 15-year agreement buys 2.7GW across PJM.

Infrastructure

EdgeCore, US Signal push data center ABS past $1 billion

EdgeCore's $521 million green ABS closed on a Santa Clara campus, more than double its previous Phoenix issue.

Infrastructure

13 states attempted data center moratoriums in 2026

New York, Oregon and Texas have statewide bans, Data Center Dynamics reports.

From other sections