Google and Voltus target one gigawatt of virtual power plant capacity in PJM

The companies described the plan Thursday as a way to free space on an energy-strapped grid for data centers.

At a glance

  1. The California-based Voltus would work with the energy use of thousands of homes and businesses.
  2. A gigawatt here is a target, not capacity already contracted or delivered to PJM.
  3. Google applied the same logic in its PG&E virtual plant, which this publication covered in September.

Google and Voltus said Thursday they are going after a gigawatt of virtual power plant capacity in PJM Interconnection, Canary Media reported. The California-based Voltus would work with the energy use of thousands of homes and businesses.

A gigawatt here is a target, not capacity already contracted or delivered to PJM. Canary Media described the plan as Google raising its ambition on using demand to free space on an energy-strapped grid for data centers.

Google applied the same logic in its PG&E virtual plant, which this publication covered in September.

Reported by the Energy Transition desk from Canary Media. Published . Corrections

Related

Infrastructure

Google and Voltus expand PJM virtual power plant to 1,170 MW

The expansion adds 1,070 MW to the June 100 MW program, with a three-to-four-year ramp and a 2040 term.

Infrastructure

Google adds 1,070 MW to Voltus virtual power plant in PJM

The expansion takes the June agreement to 1,170 MW, with Voltus expecting a three- to four-year ramp and a contract running through 2040.

Infrastructure

Google and Voltus expand PJM virtual power plant to 1GW from 100MW

The roughly three-year agreement pays participating homes and businesses for cutting demand at peak and builds on a June deal.

Infrastructure

US wind orders hit 2.8 GW in Q2 before tax credit cutoff

Wood Mackenzie keeps a 39 GW onshore outlook through 2030 and says more than half of the 2026–2028 pipeline is operating or under construction.

Infrastructure

MISO 120-day load study draws state, Google objections at FERC

Eleven state utility commissions backed OMS's protest; MISO files a cost-allocation framework next month.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections