Google confirms 506-acre Project Clydesdale data center near Tulsa

The company's $15 billion Oklahoma buildout includes water-line upgrades for Washington County Rural Water District and grid commitments in Tulsa County.

At a glance

  1. Data Center Dynamics reported the disclosure.
  2. Beale Infrastructure is the developer of record.
  3. The site sits on Cherokee Nation land.

Google has confirmed it is the company behind Project Clydesdale, the 506-acre data center campus near the Cherokee Industrial Park in Owasso, outside Tulsa. Data Center Dynamics reported the disclosure. The site extends an Oklahoma footprint that already totals $15 billion.

Beale Infrastructure is the developer of record. The county Board of Commissioners approved the campus in September 2025, with construction beginning soon after. The development plan filed that year lays out at least one phase with three possible additional phases, each covering roughly 200,000 square feet. The project is funded by private investment of at least $700 million, later increased to $1 billion.

The site sits on Cherokee Nation land. The tribe said earlier this month it is blocking data center development on its land, though it does not hold direct regulatory control over this project, according to Data Center Dynamics.

Google's Oklahoma history goes back to Pryor, where it opened its first state campus in 2011 and has expanded at regular intervals since. It is also working on campuses in Stillwater and Sand Springs. In August 2025 the company committed $9 billion to cloud and AI infrastructure in the state. Data Center Dynamics puts the total investment at $15 billion.

Google is funding and installing 1.5 miles of new water lines and infrastructure upgrades for the Washington County Rural Water District, and has committed to paying its power and water needs along with related upgrades. Trystine Payfer, Google's public affairs manager for Oklahoma, described the work as a long-term commitment to Tulsa County that begins with strengthening the local energy grid.

Google is absorbing utility costs to secure the site, and the phase structure suggests the campus is built with expansion in mind. Meta is also developing in Tulsa, according to Data Center Dynamics, making this a two-hyperscaler metro. The data halls will sit on tech-company balance sheets; the water lines, grid upgrades, and land rights are where outside capital finds work.

Reported by the Data centers & fiber desk from Data Center Dynamics. Published . Corrections

Related

Infrastructure

DOE offers Vistra a $4.2 billion conditional loan for 433 MW of nuclear uprates

The commitment is tied to Vistra's 2.6-gigawatt Meta agreement and would preserve roughly 4 gigawatts of PJM nuclear, with funding awaiting technical, legal, environmental and financial reviews.

Infrastructure

Bain puts a $6 trillion revenue test on the AI data center buildout

The firm projects $5 trillion to $6.5 trillion of data center spending through 2030 and says capital is not the near-term issue; power, electrical labor and local opposition are.

Infrastructure

Crusoe files for a $4.8bn data center campus in Jayton, Texas

The two buildings are slated to go live in 2029, and the filings name no tenant, landowner or power source.

Infrastructure

Tata Communications plans $450 million India fiber build

The first of three phases runs the Mumbai-Pune-Hyderabad-Chennai corridor, a route Tata describes as key to Indian AI and hyperscale growth.

Infrastructure

Vertiv Q3 sales rise 61% and orders double

The power and cooling supplier lifted its 2026 sales guidance to $14.45 billion to $14.85 billion.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections