O-Green's €7.4bn Spain campus has permits for 90 of 570MW

The Oman-affiliated fund's San Mateo de Gállego plan is reported to replace Vantage's €3.2 billion project, leaving 480MW without a described permit path.

€7.4bnSpain campus has permits for 90 of 570MW

At a glance

  1. The remaining 480MW has no described permit path, and the terms of the replacement were not described.
  2. A lease at the campus could attach to the permitted 90MW or the unpermitted 480MW, and per-megawatt revenue across the full build depends on who carries interconnection cost if later capacity slips.
  3. The €7.4 billion spread across 570MW works out to about €13 million per megawatt.

O-Green's planned data center campus at San Mateo de Gállego in Spain is valued at €7.4 billion and sized at 570MW, but grid permits cover only the first 90MW phase.

O-Green is described as an Oman-affiliated fund, and its San Mateo de Gállego plan is reported to replace Vantage's €3.2 billion project. The remaining 480MW has no described permit path, and the terms of the replacement were not described.

A lease at the campus could attach to the permitted 90MW or the unpermitted 480MW, and per-megawatt revenue across the full build depends on who carries interconnection cost if later capacity slips. A campus with 570MW of secured grid capacity supports a different revenue schedule than one where only the first 90MW has a path to power.

The €7.4 billion spread across 570MW works out to about €13 million per megawatt. The permitted 90MW is about 16% of the total, or roughly €1.2 billion pro rata, though the plan does not break cost down by phase.

The plan gives no date for bringing on capacity beyond the first 90MW. Whoever holds the interconnection risk — the fund, a tenant or the grid operator — determines how much of the €7.4 billion converts from a proposal into capital spending.

Reported by The Wrap desk from Infra Capital Week coverage of O-Green's San Mateo de Gállego campus, Infra Capital Week coverage of Krolmap's La Legua campus and Infra Capital Week coverage of the Actyus/Adequita/Nethits edge fund. Published . Corrections

Private Wealth Daily member access

Continue this analysis

Get the complete Infrastructure analysis and every detail that follows.

Enter a valid work email to continue reading.

Private Infrastructure Daily, from Private Wealth Daily. Unsubscribe anytime.

Full featuresIn-depth analysis and exclusive reporting.
Source-backed contextEvidence, context and the complete story.
One login across the networkAccess every Daily Network publication.

Related

Infrastructure

Umatilla permit freeze threatens $5 billion in data center investment

City says projects could be set back two years as BLM weighs 35 data center applications on western public land.

Infrastructure

Actyus, Adequita and Nethits plan €20 million Edge fund

Andbank will distribute the venture capital vehicle to high-net-worth and institutional investors once Spain's CNMV authorizes the launch.

Infrastructure

O-Green plans €7.4bn, 570MW data center campus in Spain

The Oman-affiliated fund's San Mateo de Gállego plan, reported to replace Vantage's €3.2bn project, holds grid permits for only its first 90MW phase.

Infrastructure

EdgeCore, US Signal push data center ABS past $1 billion

EdgeCore's $521 million green ABS closed on a Santa Clara campus, more than double its previous Phoenix issue.

Infrastructure

13 states attempted data center moratoriums in 2026

New York, Oregon and Texas have statewide bans, Data Center Dynamics reports.

From other sections