Nscale's Glomfjord data center six months behind schedule as IPO nears

Only 6.4MW of the Norwegian site's planned 30MW is operational, according to a Bloomberg report relayed by Data Center Dynamics.

At a glance

  1. The report cites people close to the project and public records for the setbacks: construction delays, local regulations, cooling-system leaks and a transformer fire.
  2. Nscale is preparing an initial public offering, with reports suggesting it could seek a valuation of up to $35 billion.
  3. Nscale reports $103 billion in total contracted value, largely contracts with Anthropic and Microsoft.

Nscale's Glomfjord data center in Norway is about six months behind schedule, with 6.4MW of a planned 30MW operational, according to a Bloomberg report relayed by Data Center Dynamics.

The report cites people close to the project and public records for the setbacks: construction delays, local regulations, cooling-system leaks and a transformer fire. Bloomberg also reports that Nscale towed in the Kalmar floating hotel to house construction workers nearby, a step aimed at speeding construction.

Nscale is preparing an initial public offering, with reports suggesting it could seek a valuation of up to $35 billion. Its prospectus, published in September, lists five active data centers totaling 55MW, with 12 more in development, and includes construction delays, construction site accidents and permit delays among its risk factors.

Nscale reports $103 billion in total contracted value, largely contracts with Anthropic and Microsoft. Revenue for the six months to the end of June 2026 came to $140.6 million. The company says that figure is up 1,252 percent year over year. Losses were $1.02 billion, compared with $368.9 million in the same period of 2025.

Nscale's half-year loss dwarfed its revenue

Six months to end of June 2026, compared with the same period a year earlier

  • H1 2026 net loss$1K
  • H1 2025 net loss$368.9M
  • H1 2026 revenue$140.6M
Source: Company IPO prospectus via Data Center Dynamics
Show as table
ItemValue ($M)
H1 2026 net loss$1K
H1 2025 net loss$368.9M
H1 2026 revenue$140.6M

Reported by the Data centers & fiber desk from Data Center Dynamics and Bloomberg (cited within the DCD report). Published . Corrections

Related

Infrastructure

Nscale's $3bn US IPO puts a $51bn backlog to the test

The UK neocloud aims for a September listing with Goldman and JPMorgan, betting public investors will pay infrastructure prices for a $51bn contracted-revenue backlog while it funds a 10GW buildout.

Infrastructure

Nvidia in talks to invest in Firmus after neocloud scrapped its IPO

The Information reports talks, not an agreement; a several hundred million dollar ticket would be a fraction of the $2bn–$3bn private raise Bloomberg reported Firmus was seeking.

Infrastructure

Cadence launches Munich AI data center with Nvidia chips

The site hosts OnCloud, Reality Digital Twin and the Millennium M2000; OnCloud is available to European customers now.

Infrastructure

Forum Edge signs $94.4M Nvidia B300 reservation with Fireworks

The 36-month Dallas capacity deal is the joint venture's first contracted customer commitment.

Private Infrastructure Dailyfrom Private Wealth Daily

Energy transition, digital infrastructure and core-plus funds. Daily at 7:25 a.m. ET.

Free. Every morning. Unsubscribe from any edition in one click.

From other sections